Annual leave scheduling

Changing approved annual leave in China: what should the employer do?

A China manager has approved annual leave, but headquarters now needs the employee for a project. Changing the HR-system status does not settle whether the employee must return or whether leave pay is due. For ordinary enterprise employment in mainland China, first identify what is changing: the dates within this year, a move into the next year, or leave that will no longer be arranged. Each needs a supported decision.

1. Preserve the approval before proposing a change

Export the original request, approved dates, approver, messages and leave balance before editing the system. Check the employment contract, collective agreement and applicable leave policy, including any notice or cancellation commitments. Separate statutory annual leave from extra company leave. Article 13 of the Enterprise Measures requires employers to honour more favourable provisions on leave days or unused-leave pay.

Confirm whether the employee has already started the leave, booked travel or arranged caregiving, and why their work is now needed. These facts affect whether the proposal is practicable. An overseas manager’s request should reach the China employer’s authorised decision-maker; it should not silently overwrite the earlier approval or create a retrospective absence entry.

2. For a change within the year, consult on a workable replacement

Article 5 of the Regulation and Article 9 of the Enterprise Measures require scheduling in light of production and work needs while considering the employee’s wishes. The Regulation permits leave in one block or separate periods within the year. These provisions do not create a general right to cancel any approved holiday at any time, or prescribe a universal minimum number of days’ notice for changing an approval. Check applicable local rules and the employer’s own commitments before giving a deadline.

Explain the specific operational need, test cover by another employee or a shorter interruption, and offer concrete replacement dates. Written agreement on the revised schedule is a useful way to control dispute risk; this recommendation should not be confused with the express statutory consent requirements for carryover or not arranging leave. Record the employee’s response and the outcome, rather than treating silence as acceptance.

3. Carryover and not arranging leave require a different decision

Under Article 5 of the Regulation, annual leave is generally taken within the year; where production or work characteristics genuinely require it, it may be arranged across one subsequent year. Article 9 of the Enterprise Measures requires the employee’s consent where work needs prevent arranging leave or require carryover across one year. Article 18 defines the year as the calendar year. A group policy of rolling unused days forward indefinitely is not a substitute for these conditions.

Keep a carryover record showing the relevant leave year, number of days, business reason, employee consent and proposed dates in the next year, with someone responsible for follow-up. If the company instead decides not to arrange all or part of the leave, identify the unused days and payment obligation separately. Consent to keep working because of a project does not by itself waive unused-leave pay.

4. Keep work, leave pay and cancellation costs separate

Record work actually performed after the change and correct the leave ledger so that the same period is not automatically treated as both work and leave taken. Article 10 of the Enterprise Measures requires payment within the current year for leave not arranged with consent, or arranged below the entitlement, at 300% of daily wage income, including normal wages already paid. If the normal 100% was fully paid, the usual additional amount is 200%. A later software balance alone does not prove that leave was actually taken or that payment was made.

The Article 10 exception requires that the employer arranged leave and the employee, for personal reasons, requested in writing not to take it; only normal wages may then be paid. An employer-initiated project recall should not be relabelled as that personal request. Non-refundable travel or cancellation charges are a separate issue: review the evidence, applicable commitments and a possible agreed reimbursement. These two national leave instruments do not set a universal fixed reimbursement amount for cancelling approved leave.

5. Resolve a disputed recall before considering discipline

If the employee declines the revised dates or cannot return immediately, review the original approval, the proposed change, notice actually received and their explanation. Do not infer unauthorised absence merely because a manager reversed the system status. Dismissal for serious breach of rules under Article 39(2) of the PRC Labor Contract Law requires an established serious breach; Article 4 also matters to the lawful adoption and communication of the relevant rules. A disputed leave change alone does not establish those conditions.

Prepare the original approval and policy versions, a dated business explanation, staffing alternatives, employee communications, booking or cancellation evidence, revised dates, attendance and payroll records. Management should decide who confirms the arrangement and who verifies that replacement leave or required payment actually occurs. An initial consultation can start with the China employer, work city, approved dates, proposed change and any response deadline; detailed employee records can follow through agreed confidential channels.

Legal sources

Official sources · Checked 2026-11-12. Translations are for reference and are not official legal texts.

General information about mainland China. The facts, applicable dates and local rules require individual review.

Jianxing Pan
Jianxing Pan

Partner, Beijing ChangAn Law Firm
China-qualified since 2019 · Beijing & Shenzhen

Review a proposed change to approved China annual leave

Check the approval, replacement dates and pay consequences before recalling the employee or recording absence.